|
|||||||||||||||
PROJECT UPDATE PENDING - TO OCCUR WEEK OF 7/25/05Project Information
DETAILED
DESCRIPTIONS- This
section provides a more detailed description of the various segments,
including information on project phasing and cost.
Segment 2 Segment
2 will ultimately be a 4-lane divided highway with interchanges between
Lone Tree Way and to Balfour Road. The first phase of the project
has recently been completed and is now open to traffic. Two lanes were
constructed with this phase with signalized intersections at Lone Tree
Way, new Sand Creek Road and Balfour Road. These intersections are future
interchange locations. Lone Tree Way was also widened to 4-lanes
between Heidorn Ranch Road and Jeffrey Way and sewer, gas and water
pipelines installed and phone, cable and electrical lines undergrounded.
This segment cost approximately $22 million to construct including
engineering and right of way costs and the work at Lone Tree Way. This section will remain open to
traffic and operate like a local road until the other sections of the
Bypass are constructed and taken over by Caltrans. The Authority has
contracted with the City of Brentwood to maintain the road and to provide
police services.
|
|
||||||||||||||
| About the State Route 4 Bypass Authority | Project Information | Project Vicinity Maps | Contacts | |Home| |